New Brewery Photo Blog

  • Back to work after the long weekend!
    22 Feb 2012
  • End of a good work week!
    18 Feb 2012
  • Tying down the beams on the large V post!
    16 Feb 2012
  • V post is up!
    15 Feb 2012
  • Getting ready for the second of three V posts!
    14 Feb 2012
  • Continuing to build the exterior wall
    13 Feb 2012
  • The walls continue
    10 Feb 2012
  • Continue to build the roof and add sections to the outer wall
    9 Feb 2012
  • More trucks arrive with beams for the other 3 sections
    8 Feb 2012
  • More Beams arrive as they finish off the rafters!
    7 Feb 2012
  • More Beams arrive as they finish off the rafters!
    7 Feb 2012
  • The end of the week and a surprize visit from the powder hound
    4 Feb 2012
  • The Rafters are assembled and the tie in beams erected!
    3 Feb 2012
  • Continuing with the tie in rafters
    2 Feb 2012
  • More beams and the first of the three triangle beams that hold the massive roof go up!
    1 Feb 2012
  • More beans go up!
    31 Jan 2012
  • The first part of the building is erected!!
    28 Jan 2012
  • The first beams are erected!!
    27 Jan 2012
  • Large day of dileveries as we get set to build up!
    26 Jan 2012
  • Crane gets erected on site!
    25 Jan 2012